Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 08/20/2010 |
Comment Period | 10/17/2011 |
Decision | 06/2012 (Estimated) |
Implementation | 07/2012 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Arrowhead Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Strawberry Peak Communications Tower Replacement Project
Decision Signed Date: 06/08/2012
Legal Notice Date: 06/14/2012
Forests:
San Bernardino National Forest
Districts:
Arrowhead Ranger District
States:
California
Counties:
San Bernardino
Legal Land Description:
T.2N., R.3W., Sec. 30 / 34°13’80”N, 117°14’35”W
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Heidi Hoggan
P.O. Box 350
Skyforest, CA 92385
909-382-2945
hhoggan@fs.fed.us
Last Updated: 6/28/2012