Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 08/30/2019 |
Decision | 02/2020 (Estimated) |
Implementation | 03/2020 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
San Jacinto Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Frontier May Valley/Bonita Vista Fiber Optic Lines Site Project
Decision Signed Date: 02/18/2020
Forests:
San Bernardino National Forest
Districts:
San Jacinto Ranger District
States:
California
Counties:
Riverside
Legal Land Description:
Sections, 28, 29, 31, 32, Township 5 South, Range 3 East, S.B.B.M., Idyllwild Quadrangle
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Heidi Hoggan
54270 Pinecrest Avenue
Idyllwild, CA 92549
909-382-2945
heidi.hoggan@usda.gov
Last Updated: 2/18/2020