MILL FLAT CREEK ROADS MANAGEMENT
A proposal to seasonally close the Davis Road (FR 12S01) (approximately 12/1 - 4/15 based on weather conditions) and to decommission 13 forest roads or portions of roads (a total of 3.3 miles) within the Mill Flat Creek Critical Aquatic Refuge.
Project Summary
Location Summary:
Mill Flat Creek drainage
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 02/17/2012 |
| Comment Period | 01/19/2017 |
| Objection Period Start | 03/01/2017 |
| Decision | 04/2017 (Estimated) |
| Implementation | 06/2017 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Hume Lake Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Wildlife, Fish, Rare Plants; Watershed Management; Road Management
Project Activity:
Road Decommissioning; Species Habitat Improvements; Road Maintenance; Travel Management; Watershed Improvements
Current Status:
Completed
Project Decision Information
MILL FLAT CREEK ROADS MANAGEMENT
Decision Signed Date: 04/27/2017
Forests:
Sequoia National Forest
Districts:
Hume Lake Ranger District
States:
California
Counties:
Fresno
Legal Land Description:
T13S, R26-27E MDB&M
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jeff Cordes
35860 East Kings Canyon Rd
Dunlap, CA 93621
559-338-2251
jcordes@fs.fed.us
Last Updated: 7/18/2017