Black Mountain Grove fuels reduction project
The project will reduce fuel loads and remove ladder fuels through a combination of dead and live tree removal and duff removal around the base of monarch Giant Sequoia trees.
Project Summary
Location Summary:
Tule River watershed
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 07/22/2022 |
Decision | 07/2022 (Estimated) |
Implementation | 08/2022 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (6), 36 Cfr 220.6(E)(6); 32.2 (25), 36 Cfr 220.6(E)(25)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Western Divide Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Vegetation Management (Other Than Forest Products)
Project Activity:
Forest Vegetation Improvements
Current Status:
Completed
Project Decision Information
Decision Memorandum for the Chief R5 Emergency Response Giant Sequoia
Decision Signed Date: 07/22/2022
Forests:
Sequoia National Forest
Districts:
Western Divide Ranger District
States:
California
Counties:
Tulare
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Gretchen Fitzgerald
32588 Highway 190
Springville, CA 93265
(559) 920-2957
gretchen.fitzgerald2@usda.gov