SCE Big Creek Life Extension Project
SCE has 2 crib walls to support transmission line towers. The walls are deteriorating wood and will be replaced with new steel crib walls.
Project Summary
Location Summary:
Along Railroad Grade approximately 2 miles west of Stevenson Creek.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 03/17/2011 |
Decision | 11/2011 (Estimated) |
Implementation | 05/2012 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
High Sierra Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Big Creek Life Extension Project, Transmission Line Crib Wall Replacement
Decision Signed Date: 11/03/2011
Forests:
Sierra National Forest
Districts:
High Sierra Ranger District
States:
California
Counties:
Fresno
Legal Land Description:
T9S, R24E, Section 9
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Annette Lambert
29688 Auberry Rd.
Prather, CA 93651
(559) 855-5355 x3338
alambert@fs.fed.us
Last Updated: 11/4/2011