Sierra Telephone Bass Lake Fiber Project
This project involves the proposed installation of approximately 10,100 feet of buried conduit with fiber optic cable and empty conduit for future use from existing facilities on USFS Road 7S24.
Project Summary
Location Summary:
South side of Bass Lake, between The Forks and Rocky Point.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 08/13/2015 |
Decision | 11/2016 (Estimated) |
Implementation | 01/2017 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Bass Lake Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Sierra Telephone Company, Inc. Bass Lake New Fiber Optic Cable
Decision Signed Date: 11/21/2016
Forests:
Sierra National Forest
Districts:
Bass Lake Ranger District
States:
California
Counties:
Madera
Legal Land Description:
T7S, R22E, Sections 22,23
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Annette Lambert
57003 Road 225
North Fork, CA 93643
559-855-5355 x3338