PO PUD Electric Transmission Line Addition
Addition of approximately 2500 feet of buried electric transmission line within an existing road prism to service a private parcel. New line will connect to existing electrical infrastructure on adjacent Sullivan Creek Rd
Project Summary
Current Status:
Completed
Location Summary:
East of Metaline Falls, WA on Sullivan Creek Road
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 04/13/2022 |
| Decision | 08/2022 (Estimated) |
| Implementation | 09/2022 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Sullivan Lake Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Project Decision Information
PO PUD Powerline-Bud Moon Road Addition
Decision Signed Date: 08/22/2022
Forests:
Colville National Forest
Districts:
Sullivan Lake Ranger District
States:
Washington
Counties:
Pend Oreille
Legal Land Description:
NW 1/4 Section 25, T39N, R43E
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Anna Lowell
12641 Sullivan Lake Road
Metaline Falls, WA 99153
509-684-7266
anna.lowell@usda.gov
Last Updated: 8/23/2022