49 Degrees North Chair #1 Tower Addition
A new tower will be installed between existing towers 18 & 19 to improve the safety of lift operations.
Project Summary
Location Summary:
49 Degrees North Mountain Resort permit area
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 06/13/2012 |
| Comment Period | 06/13/2012 |
| Decision | 08/2012 (Estimated) |
| Implementation | 08/2012 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (5), 36 Cfr 220.6(D)(5)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Newport Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
49 Degrees North Chair #1 Tower Addition
Decision Signed Date: 08/14/2012
Legal Notice Date: 08/15/2012
Forests:
Colville National Forest
Districts:
Newport Ranger District
States:
Washington
Counties:
Pend Oreille
Legal Land Description:
T32N, R41E, NE1/4 NE1/4 Sec 12
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Kevin Walton
315 North Warren
Newport, WA 99156
509-447-7300
kawalton@fs.fed.us
Last Updated: 8/20/2012