Mill Pond-Sullivan Connector Trail
This project would brush out and place tread in ~1,455 feet of an overgrown existing road prism (Road 3300230) on the south end, construct about 1,612 feet of new trail, and then placing ~1,500 feet of tread and brushing out an existing road prism.
Project Summary
Location Summary:
NE WA, W of Outlet Creek inlet on the North edge of Sullivan Lake to Mill Pond
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 02/25/2020 |
Decision | 02/2022 (Estimated) |
Implementation | 05/2022 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (1), 36 Cfr 220.6(E)(1)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Newport Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Recreation Management
Project Activity:
Trail Management
Current Status:
Completed
Project Decision Information
Mill Pond-Sullivan Connector Trail
Decision Signed Date: 02/17/2022
Forests:
Colville National Forest
Districts:
Newport Ranger District
States:
Washington
Counties:
Pend Oreille
Legal Land Description:
T39N;R44E;S30
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Allison Ginn
315 North Warren
Newport, WA 99156
509-380-3586
Allison.Ginn@usda.gov