Rattlesnake Hazardous Fuels Reduction Project
Remove hazardous fuels from the Rattlesnake project area. An interactive story map for this project can be found here!
Project Summary
Location Summary:
Coffeepot, Cow, and Rattlesnake subwatersheds
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 11/28/2018 |
| Objection Period Start | 06/12/2019 |
| Decision | 09/2019 (Estimated) |
| Implementation | 10/2019 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Hfra Title I: Wildland-Urban Interface
Lead Management Unit:
Emigrant Creek Ranger District
Notice and Comment Regulation:
218 (2013) HFRA
Project Purpose:
Vegetation Management (Other Than Forest Products); Fuels Management
Project Activity:
Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Green)
Current Status:
Completed
Project Decision Information
Rattlesnake Hazardous Fuels Reduction Project Decision Notice FONSI
Decision Signed Date: 09/13/2019
Forests:
Malheur National Forest
Districts:
Emigrant Creek Ranger District
States:
Oregon
Counties:
Harney
Legal Land Description:
See attached map.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Lori Bailey
265 Highway 20 South
Hines, OR 97738
541-573-4300
labailey@fs.fed.us