OTEC Bury Overhead Powerlines
Bury two existing overhead distribution lines for the reduction of fire start risk on ECRD.
Project Summary
Location Summary:
Two locations off 69 kV line to Crow Flat Guard Station and private property.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 08/19/2020 |
Decision | 08/2020 (Estimated) |
Implementation | 09/2020 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Emigrant Creek Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
OTEC Bury Overhead Powerlines
Decision Signed Date: 08/26/2020
Forests:
Malheur National Forest
Districts:
Emigrant Creek Ranger District
States:
Oregon
Counties:
Harney
Legal Land Description:
T. 20 S., R. 31 E., Sections 13 and 23
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Melissa Ward
265 Highway 20 South
Hines, OR 97738
541-573-4300
mward@fs.fed.us
Last Updated: 8/31/2020