Wolf Vegetation and Fuels Management Project
The general purpose of entering this project area is to contribute to the resiliency of the landscape and to promote vegetative conditions that are similar to what occurred historically.
Project Summary
Location Summary:
The Wolf project area is approximately 50 miles east of the city of Prineville.
Project Milestones:
| Milestone | Date |
|---|---|
| NOI in Federal Register | 04/05/2013 |
| DEIS NOA in Federal Register | 01/31/2014 |
| FEIS NOA in Federal Register | 06/13/2014 |
| Objection Period Start | 06/13/2014 |
| Decision | 09/2014 (Estimated) |
| Implementation | 09/2014 (Estimated) |
Expected Analysis Type:
Environmental Impact Statement
Special Authority:
Not Applicable / Other
Lead Management Unit:
Paulina Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Vegetation Management (Other Than Forest Products)
Project Activity:
Forest Vegetation Improvements
Current Status:
Completed
Project Decision Information
Wolf Fuels and Vegetation Management Project
Decision Signed Date: 09/23/2014
Forests:
Ochoco National Forest
Districts:
Paulina Ranger District
States:
Oregon
Counties:
Crook; Wheeler
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jeff Marszal
3160 NE Third Street
Prineville, OR 97754
541-416-6500
jmarszal@fs.fed.us
Last Updated: 9/23/2014