Quantum Communications Fiber Optic Cable Special Use Permit Reissue
Issue of a new term permit to replace an expired permit that covered 48 acres (19.8 miles/20' width) and included 0.2 miles of underground cable and 19.6 miles of overhead cable. No changes to the exisiting facilities or activities is proposed.
Project Summary
Location Summary:
Starting point is BPA tower (see legal location); cable extends west to Madras area then south to Redmond area.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 09/25/2013 |
| Comment Period | 09/27/2013 |
| Decision | 12/2013 (Estimated) |
| Implementation | 02/2014 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (15)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Crooked River Natl Grassland
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Quantum Communications - 823 Fiber Optic Cable Special Use Permit
Decision Signed Date: 12/09/2013
Legal Notice Date: 02/03/2014
Forests:
Ochoco National Forest
Districts:
Crooked River Natl Grassland
States:
Oregon
Counties:
Jefferson
Legal Land Description:
T. 11 S., R 14 E., Sec. 11.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Heidi Scott
813 S.W. Hwy. 97
Madras, OR 97741
541-416-6632
hscott02@fs.fed.us
Last Updated: 2/3/2014