Mount Pisgah Communications Site, Oregon State Radio Project Facility
The purpose is to issue a communication use lease for construction and operation of a new communications facility on Mount Pisgah to support communications equipment for the Oregon State Radio project.
Project Summary
Location Summary:
Top of Mount Pisgah, Section 8, T13S, R21E, Williamette Meridian
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 10/07/2013 |
| Comment Period | 12/06/2013 |
| Decision | 07/2014 (Estimated) |
| Implementation | 08/2014 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Ochoco National Forest All Units
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Mount Pisgah Communications Site Oregon State Radio Project Facility
Decision Signed Date: 07/03/2014
Mount Pisgah Communications Site, Oregon State Radio Project Facility
Decision Signed Date: 07/03/2014
Forests:
Ochoco National Forest
Districts:
Paulina Ranger District
States:
Oregon
Counties:
Wheeler
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Heidi Scott
3160 N.E. 3rd Street
Prineville, OR 97754
541-416-6632
hscott02@fs.fed.us
Last Updated: 2/2/2016