City of Mitchell Spring Maintenance
The City of Mitchell wants to extend their outflow lines on two spring developments. Spring 1, they propose to extend the line under the adjacent road. They propose to repair a water meter along their pipeline. Spring 2 they want to extend 20ft.
Project Summary
Location Summary:
Northeast of Bridge Creek Wilderness Area
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 05/27/2022 |
| Decision | 08/2022 (Estimated) |
| Implementation | 09/2022 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Paulina Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
City of Mitchell Water Development Maintenance
Decision Signed Date: 08/10/2022
Forests:
Ochoco National Forest
Districts:
Paulina Ranger District
States:
Oregon
Counties:
Wheeler
Legal Land Description:
T 12 S., R 21 E., Sec 34
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Heather Jackson
3160 NE Third Street
Prineville, OR 97754
541-383-4025
heather.jackson@usda.gov
Last Updated: 8/11/2022