Jefferson Solar Powerline Project
Jefferson Solar, LLC has proposed a 170 foot wide right-of-way to house two parallel 230 kV transmission lines, approximately 4,700 foot in length, across Crooked River National Grassland for interconnection of a solar facility to the power grid.
Project Summary
Location Summary:
Between Madras and Terrebonne, just south of Juniper Butte and approximately 1 mile west of Hwy 97.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 12/08/2023 |
| Decision | 07/2024 (Estimated) |
| Implementation | 07/2024 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Forest Service Energy Implementation Plan
Lead Management Unit:
Crooked River Natl Grassland
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Electric Transmission; Special Use Authorizations
Current Status:
Completed
Project Decision Information
Special Use Permit for Jefferson Solar Powerline
Decision Signed Date: 07/30/2024
Forests:
Ochoco National Forest
Districts:
Crooked River Natl Grassland
States:
Oregon
Counties:
Jefferson
Legal Land Description:
T13S, R12E, Section 12 & T13S, R13E, Section 7
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Heather Jackson
813 S.W. Hwy. 97
Madras, OR 97741
541-416-6632
heather.jackson@usda.gov