Lake Cushman Bridge ERFO repair
Permanent repair to the west end of the Lake Cushman Bridge, located on FSR 2451000 at mile post 0.2, damaged in a 2007 storm. The existing temporary repair does not provide safe and adequate vehicle access to the Elk Creek and Four Stream areas.
Project Summary
Location Summary:
West end of the Lake Cushman Bridge, at mile post 0.2 on FSR 2451000
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 04/01/2011 |
Decision | 07/2011 (Estimated) |
Implementation | 08/2011 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (4), 36 Cfr 220.6(D)(4)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Hood Canal Ranger District / Hoodsport
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Watershed Management; Road Management
Project Activity:
Road Improvements/Construction
Current Status:
Completed
Project Decision Information
Lake Cushman Bridge ERFO repair
Decision Signed Date: 07/08/2011
Forests:
Olympic National Forest
Districts:
Hood Canal Ranger District / Hoodsport
States:
Washington
Counties:
Mason
Legal Land Description:
T23N, R05W, section 9
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Shannon Henriquez
295142 Highway 101 S.
Quilcene, WA 98376
360-956-2264
shenriquez@fs.fed.us
Last Updated: 9/30/2011