Mount Avery Spur Road Project
Construct about 330 feet of new road on Forest Service lands from the end of Forest Service Road 5201-200 to the private parcel in T32S, R13W, Section 16. Applicant requests permission to use and maintain the road for perpetual timber management.
Project Summary
Location Summary:
Sixes River and South Fork Sixes River watersheds approximately 15 miles east of Port Orford, Oregon.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 11/22/2011 |
Comment Period | 11/10/2014 |
07/28/2016 | |
Objection Period Start | 06/03/2016 |
Decision | 07/2016 (Estimated) |
Implementation | 09/2016 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Powers Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Road Management; Special Use Management
Project Activity:
Road Improvements/Construction
Current Status:
Completed
Project Decision Information
Mount Avery Spur Road Special Use Permit Request
Decision Signed Date: 07/28/2016
Forests:
Rogue River-Siskiyou National Forest
Districts:
Powers Ranger District
States:
Oregon
Counties:
Curry
Legal Land Description:
T32S, R13W, Section 22
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Donald Kay
42861 Highway 242
Powers, OR 97466
541-439-6223
dkay@fs.fed.us
Last Updated: 1/6/2021