Special Use Permit Renewals at J. Herbert Stone Nursery
A decision memo is being prepared to authorize renewal of 4 existing special use authorizations: 2 power lines, 1 natural gas line, and 1 telephone line at the J. Herbert Stone Nursery. The permit would be issued for a 20 year term.
Project Summary
Location Summary:
J. Herbert Stone Nursery
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 01/01/2013 |
Comment Period | 01/15/2013 |
Decision | 05/2013 (Estimated) |
Implementation | 06/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (15)
Special Authority:
Not Applicable / Other
Lead Management Unit:
J. Herbert Stone Nursery
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Special Use Permit Renewals at J. Herbert Stone Nursery Decision Memo
Decision Signed Date: 05/09/2013
Forests:
Rogue River-Siskiyou National Forest
Districts:
J. Herbert Stone Nursery
States:
Oregon
Counties:
Jackson
Legal Land Description:
T. 37 S., R. 2 W., Sec. 15 and 16, Willamette Meridian
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Gary Einck
2606 Old Stage Road
Central Point, OR 97502
541-618-2037
geinck@fs.fed.us