Siskiyou Mountains Ranger District request to issue a Special Use Permit request for temporary road
Murphy Timber Investments is proposing to build approximately 850 feet of temporary road and a landing to facilitate salvage of fire-damaged trees from their lands.
Project Summary
Location Summary:
Location is in the Whiskey Creek drainage 3-4 miles west of Applegate Lake .
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 02/01/2018 |
Decision | 04/2018 (Estimated) |
Implementation | 05/2018 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Siskiyou Mountains Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Siskiyou Mountains Ranger District request to issue a Special Use Permit request for temporary road
Decision Signed Date: 04/05/2018
Forests:
Rogue River-Siskiyou National Forest
Districts:
Siskiyou Mountains Ranger District
States:
Oregon
Counties:
Jackson
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Donald Boucher
6941 Upper Applegate Road
Jacksonville, OR 97530-9314
541-899-3840
dboucher@fs.fed.us