Mountain Line Replacement Project
Replace existing 100 yr old water transmission line, providing potable water to the residents of Baker City.
Project Summary
Location Summary:
23 miles in the Elkhorn Mountains approximately 15 miles west of Baker City.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 08/25/2014 |
Comment Period | 03/11/2016 |
Objection Period Start | 06/10/2016 |
Decision | 08/2016 (Estimated) |
Implementation | 08/2016 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other; Ira - Inventoried Roadless Area Activities Requiring Chief's Approval
Lead Management Unit:
Whitman Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Special Use Management
Project Activity:
Facility Improvements/Construction; Special Use Authorizations
Current Status:
Completed
Project Decision Information
Mountain Line Replacement Project
Decision Signed Date: 08/02/2016
Forests:
Wallowa-Whitman National Forest
Districts:
Whitman Ranger District
States:
Oregon
Counties:
Baker
Legal Land Description:
T 9 S, R 38 E; T 9 E, R 39 E
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Robert Macon
1550 Dewey Avenue
Baker City, OR 97814
541-523-1343
rmacon@fs.fed.us
Last Updated: 12/10/2019