Berkeley Electric Cooperative Hwy 17 Improvements
Improvement activities including replacement of 1.14 miles of single phase overhead line with three phases line and construction of 1.87 miles of new underground lines along US Hwy 17 Charleston County SC.
Project Summary
Location Summary:
The location oof both overhead improvements and underground construction is coincident with US Hwy 17 road shoulder.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 07/11/2013 |
Comment Period | 07/11/2013 |
Decision | 12/2013 (Estimated) |
Implementation | 01/2014 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Francis Marion Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Berkeley Electric Cooperative Hwy 17 Utility Improvements
Decision Signed Date: 12/04/2013
Legal Notice Date: 12/07/2013
Forests:
Francis Marion and Sumter National Forests
Districts:
Francis Marion Ranger District
States:
South Carolina
Counties:
Charleston
Legal Land Description:
Tracts F-92, F-113r and F1416a Francis Marion National Forest
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Amy Fore
2967 Steed Creek Road
Huger, SC 29450
843-336-2203
afore@fs.fed.us
Last Updated: 12/30/2013