Howard Creek Restoration Project
Brook trout and stream restoration project.
Project Summary
Location Summary:
Howard Creek, Keowee and Toxaway River Watershed of the upper Savannah River.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 11/26/2014 |
Comment Period | 04/03/2015 |
Objection Period Start | 05/27/2015 |
Decision | 07/2015 (Estimated) |
Implementation | 07/2015 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Francis Marion and Sumter National Forest All Units
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Watershed Management; Wildlife, Fish, Rare Plants
Project Activity:
Species Habitat Improvements; Species Population Enhancements; Watershed Improvements
Current Status:
Completed
Project Decision Information
Howard Creek Habitat Restoration
Decision Signed Date: 07/22/2015
Forests:
Francis Marion and Sumter National Forests
Districts:
Andrew Pickens Ranger District
States:
South Carolina
Counties:
Oconee
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Thomas Scott
4931 Broad River Rd.
Columbia, SC 29212-3530
423-783-2419
thomasscott@fs.fed.us
Last Updated: 7/22/2015