Central Electric Mt. Rest-Pickett Post 44Kv Transmission Line Rebuild
Central Electric Cooperative will rebuild approximately a 1 mile section of transmission line on the Andrew Pickens Ranger District replacing the wooden poles with metal poles.
Project Summary
Location Summary:
Project is located in Compartment 26
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 01/14/2022 |
Decision | 07/2022 (Estimated) |
Implementation | 07/2022 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Francis Marion and Sumter National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Central Electric Mt. Rest-Pickett Post 44Kv Transmission Line Rebuild
Decision Signed Date: 07/28/2022
Forests:
Francis Marion and Sumter National Forests
Districts:
Andrew Pickens Ranger District
States:
South Carolina
Counties:
Oconee
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Derrick Miller
4931 Broad River Rd.
Columbia, SC 29212-3530
540-265-5128
derrick.miller@usda.gov
Last Updated: 9/16/2022