Francis Marion Wetland Restoration Project
We propose mechanical and chemical treatments to reduce woody encroachment into Carolina bays and depressional wetlands across the Francis Marion.
Project Summary
Location Summary:
Project includes all ephemeral wetlands district-wide and adjacent upland areas 100-meters from the wetland edge.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 03/15/2022 |
Comment Period | 01/11/2023 |
Objection Period Start | 03/25/2023 |
Decision | 05/2023 (Estimated) |
Implementation | 06/2023 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Francis Marion Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Vegetation Management (Other Than Forest Products); Wildlife, Fish, Rare Plants
Project Activity:
Species Habitat Improvements
Current Status:
Completed
Project Decision Information
Francis Marion Wetland Restoration Project
Decision Signed Date: 05/22/2023
Forests:
Francis Marion and Sumter National Forests
Districts:
Francis Marion Ranger District
States:
South Carolina
Counties:
Berkeley; Charleston
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jestin Clark
2967 Steed Creek Road
Huger, SC 29450
843-336-2241
jestin.clark@usda.gov