Gulf South Pipeline Relocation
Relocate a section of natural gas pipeline that has become exposed due to erosion along the banks of Black Creek. New r/w 50' wide, with add'l 25' temp work space needed. Directional bore under Black Creek. Rehabilitation of abandoned r/w.
Project Summary
Location Summary:
Black Creek, upstream from Fairley Bridge Road; north of existing right-of-way.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 05/28/2014 |
Decision | 10/2019 (Estimated) |
Implementation | 12/2019 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
De Soto Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
On Hold
Forests:
National Forests In Mississippi
Districts:
De Soto Ranger District
States:
Mississippi
Counties:
Perry
Legal Land Description:
Section 27, T1S, R10W
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Alan Oglesbee
654 W. Frontage Rd.
Wiggins, MS 39577
601-528-4977
alan.oglesbee@usda.gov
Last Updated: 11/11/2023