Baldwin Gap Project
The proposed action is to harvest timber, reconstruct existing old roads, construct new system and temporary roads, do precommercial thinning, and improve wildlife habitat through the development of linear wildlife openings and seeded landings.
Project Summary
Current Status:
Completed
Location Summary:
Compartment 1, Management Areas 3B and 4C
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 03/25/2005 |
| Comment Period | 03/25/2005 |
| Decision | 09/2005 (Estimated) |
| Implementation | 11/2005 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Pisgah Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Wildlife, Fish, Rare Plants; Forest Products; Watershed Management
Project Activity:
Timber Sales (Green)
Project Decision Information
Baldwin Gap Project
Decision Signed Date: 09/27/2005
Legal Notice Date: 09/29/2005
Forests:
National Forests In North Carolina
Districts:
Pisgah Ranger District
States:
North Carolina
Counties:
Buncombe
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Ted Oprean
1001 Pisgah Hwy.
Pisgah Forest, NC 28768
(828) 877-3265
toprean@fs.fed.us
Last Updated: 9/29/2010