Pee Dee Electric SUP Amendment
This amendment would allow for a new powerline to be constructed on approximately 2 acres of National Forest System lands (NFS).
Project Summary
Current Status:
Completed
Location Summary:
Uwharrie Ranger District
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 10/02/2023 |
| Decision | 11/2023 (Estimated) |
| Implementation | 12/2023 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Uwharrie Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Electric Transmission; Special Use Authorizations
Project Decision Information
Pee Dee Electric SUP Amendment
Decision Signed Date: 11/02/2023
Forests:
National Forests In North Carolina
Districts:
Uwharrie Ranger District
States:
North Carolina
Counties:
Montgomery
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Victoria Payne
789 NC24/27E
Troy, NC 27371
2526390304
Victoria.Payne@usda.gov
Last Updated: 11/27/2023