US 64 Fill Slope Repair
Emergency repair of fill bank failure on US 64 and stabilization and revegetation of bank.
Project Summary
Current Status:
Completed
Location Summary:
US 64 between Highlands and Franklin along the Cullasaja River.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 01/11/2024 |
| Decision | 01/2024 (Estimated) |
| Implementation | 01/2024 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (20), 36 Cfr 220.6(E)(20)
Special Authority:
Not Applicable / Other
Lead Management Unit:
National Forests In North Carolina All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Watershed Management; Road Management
Project Activity:
Road Maintenance; Watershed Improvements
Project Decision Information
US 64 Fill Slope Repair
Decision Signed Date: 01/26/2024
Forests:
National Forests In North Carolina
Districts:
Nantahala Ranger District
States:
North Carolina
Counties:
Macon
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jason Herron
160 Zillicoa St.
Asheville, NC 28801
828-689-9694 ex: 112
jason.herron@usda.gov