Highway 270 Realignment (Blowout Mountain)
Construction of a climbing lane and realignment of two severe curves on approximately 0.8 miles of Highway 270.
Project Summary
Current Status:
Completed
Location Summary:
Highway 270 generally within the boundaries of the Blowout Mountain Scenic Area.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 08/04/2009 |
| Comment Period | 02/28/2010 |
| Decision | 09/2010 (Estimated) |
| Implementation | 11/2010 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Mena Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Road Management
Project Activity:
Road Improvements/Construction; Travel Management; Timber Sales (Green)
Project Decision Information
Highway 270 Realignment (Blowout Mountain)
Decision Signed Date: 09/14/2010
Legal Notice Date: 09/16/2010
Forests:
Ouachita National Forest
Districts:
Oden Ranger District
States:
Arkansas
Counties:
Montgomery
Legal Land Description:
T 1 S, R 26 W, Sections 4 and 5.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Russell Standingwater
1603 Highway 71 North
Mena, AR 71953
479-394-2382
rstandingwater@fs.fed.us
Last Updated: 7/26/2019