Oklahoma Department of Corrections' Communication Site Expansion
Amend existing lease to add a generator, propane tank, concrete pads and a fence at the Hodgen Communications Site to provide backup electricity during power outages at the Jim Hamilton Correctional Facility.
Project Summary
Current Status:
Completed
Location Summary:
Approximately 4 miles south of Heavener Oklahoma.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 06/01/2018 |
| Decision | 07/2018 (Estimated) |
| Implementation | 09/2018 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Kiamichi Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Project Decision Information
Oklahoma Department of Corrections' Communication Site Expansion
Decision Signed Date: 07/31/2018
Forests:
Ouachita National Forest
Districts:
Kiamichi Ranger District
States:
Oklahoma
Counties:
Le Flore
Legal Land Description:
Section 12, T3N, R25E
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jessica Soroka
111 South State Highway 259-A
Broken Bow, OK 74728
501-321-5226
jasoroka@fs.fed.us
Last Updated: 8/22/2018