Crystal Vista Rehabilitation
The area has suffered from soil loss and trees growing on the flat area. Heavy equipment will be used to fill in and smooth areas and clear vegetation on flatter areas to allow for digging.
Project Summary
Current Status:
Completed
Location Summary:
THe project area is located 5.7 miles northeast from Norman and 3.4 miles southeast from Mt. Ida.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 06/05/2024 |
| Decision | 08/2024 (Estimated) |
| Implementation | 09/2024 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (22), 36 Cfr 220.6(E)(22)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Womble Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Recreation Management
Project Activity:
Developed Site Management
Project Decision Information
Signed_CEandDM_Crystal Vista Rehab Project
Decision Signed Date: 08/15/2024
Forests:
Ouachita National Forest
Districts:
Womble Ranger District
States:
Arkansas
Counties:
Montgomery
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Mary Brown
P.O. Box 255
Mount, AR 71957
870-867-2101
mary.e.brown@usda.gov
Last Updated: 8/15/2024