Buck Creek AOP - Geotech Investigation
The Hoosier is proposing to authorize the subsurface and geotechnical investigation to be performed on the existing access road to facilitate the design work needed for the upcoming proposed Buck Creek AOP project.
Project Summary
Location Summary:
Approximately 6.5 miles WNW of French Lick, Indiana
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 10/29/2018 |
| Decision | 12/2018 (Estimated) |
| Implementation | 12/2018 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (8), 36 Cfr 220.6(E)(8)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Hoosier National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Buck Creek AOP - Geotech Investigation
Decision Signed Date: 12/17/2018
Forests:
Hoosier National Forest
Districts:
Brownstown Ranger District
States:
Indiana
Counties:
Martin
Legal Land Description:
Section 28, T2N, R3W
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Kathryn Slezak
811 Constitution Avenue
Bedford, IN 47421
812-547-9238
kslezak@fs.fed.us
Last Updated: 12/17/2018