Turkey Creek Day Use Area Improvement
Replacement of a wooden foot bridge that was damaged during a flood event and realignment of the trail within the floodplain and connecting to each end of the replaced foot bridge.
Project Summary
Location Summary:
T33N R5E Sec. 12; 5th Principal Meridian, Madison County, Missouri
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 03/12/2019 |
| Decision | 08/2019 (Estimated) |
| Implementation | 10/2019 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (1), 36 Cfr 220.6(E)(1)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Potosi / Fredericktown Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Recreation Management
Project Activity:
Developed Site Management; Trail Management
Current Status:
Completed
Project Decision Information
Turkey Creek Day Use Area Improvement
Decision Signed Date: 08/19/2019
Forests:
Mark Twain National Forest
Districts:
Potosi / Fredericktown Ranger District
States:
Missouri
Counties:
Madison
Legal Land Description:
T33N R5E Sec. 12; 5th Principal Meridian, Madison County, Missouri
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Christopher Woods
P.O. Box 188
Potosi, MO 63664
573-438-5427
cmwoods@fs.fed.us