Doe Run Company Lease Modifications MOBLMA 046975, MOBLMA 047477, MOBLMA 079252
Analyze effects of 3 lease modifications for approx 1550 acres to potentially add ore reserves to continue operating into the future. See https://eplanning.blm.gov/eplanning-ui/project/2016966/510 for more information.
Project Summary
Location Summary:
T.33N. R.2W. Sec. 26 & 27 - T32N. R.1W. Sec. 07, 18 & 19; T.32N. R.2W. Sec 25; T.31N. R.2W. Sec 17 & 20
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 09/23/2022 |
| Comment Period | 09/23/2022 |
| Objection Period Start | 06/09/2023 |
| Decision | 10/2023 (Estimated) |
| Implementation | 11/2023 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Nepa Document Prepared By Another Federal Agency
Lead Management Unit:
Mark Twain National Forest All Units
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations
Current Status:
Completed
Project Decision Information
Doe Run Company Lease Modifications MOBLMA 046975, MOBLMA 047477, MOBLMA 079252
Decision Signed Date: 10/11/2023
Forests:
Mark Twain National Forest
Districts:
Salem Ranger District
States:
Missouri
Counties:
Reynolds; Shannon
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
John Lacoste
401 Fairgrounds Road
Rolla, MO 65401
573-341-7479
john.lacoste@usda.gov