Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 06/06/2007 |
Decision | 08/2007 (Estimated) |
Implementation | 08/2007 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Midewin National Tallgrass Prairie All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Area Management; Recreation Management
Project Activity:
Special Area Management
Current Status:
Completed
Project Decision Information
Interim Service Campground
Decision Signed Date: 08/31/2007
Forests:
Midewin National Tallgrass Prairie
Districts:
Midewin National Tallgrass Prairie All Units
States:
Illinois
Counties:
Will
Legal Land Description:
T33N, R9E, Section 1
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Marta Witt
30239 South State Route 53
Wilmington, IL 60481
815-423-6370
mlwitt@fs.fed.us
Last Updated: 6/30/2021