Hoff Road Ditch Maintenance Project
This project will clear existing ditches of sediment and debris, remove existing culverts, replace chain link fence with barbed wire fencing and create low water crossing at two locations south of Hoff Rd.
Project Summary
Location Summary:
Areas of treatment will be south of Hoff Rd. near Road 2 East
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 03/03/2014 |
Decision | 02/2015 (Estimated) |
Implementation | 04/2015 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (4), 36 Cfr 220.6(D)(4); 32.2 (18), 36 Cfr 220.6(E)(18)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Midewin National Tallgrass Prairie All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Watershed Management; Road Management
Project Activity:
Forest Vegetation Improvements; Road Maintenance; Watershed Improvements
Current Status:
Completed
Project Decision Information
Hoff road Ditch Maintenance Project
Decision Signed Date: 02/26/2015
Forests:
Midewin National Tallgrass Prairie
Districts:
Midewin National Tallgrass Prairie All Units
States:
Illinois
Counties:
Will
Legal Land Description:
Township 34 North Range 10 E Section 36
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jeffrey Tepp
30239 South State Route 53
Wilmington, IL 60481
815-423-2164
jtepp@fs.fed.us
Last Updated: 3/3/2015