West Patrol Road Maintenance and Culvert Work
Replacing existing culvert, removing a culvert, culvert cleaning and road maintenance on West Patrol Road.
Project Summary
Location Summary:
The activities will occur along West Patrol Road on the west side of Midewin.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 07/13/2023 |
| Decision | 09/2023 (Estimated) |
| Implementation | 10/2023 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (4), 36 Cfr 220.6(D)(4); 32.2 (23), 36 Cfr 220.6(E)(23)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Midewin National Tallgrass Prairie All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Road Management
Project Activity:
Road Maintenance; Road Improvements/Construction
Current Status:
Completed
Project Decision Information
West Patrol Road Maintenance and Culvert Work
Decision Signed Date: 09/28/2023
Forests:
Midewin National Tallgrass Prairie
Districts:
Midewin National Tallgrass Prairie All Units
States:
Illinois
Counties:
Will
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Robert Hommes
30239 South State Route 53
Wilmington, IL 60481
815-423-6370
robert.hommes@usda.gov
Last Updated: 9/28/2023