Nicor Natural Gas Pipeline Maintenance 2024
Nicor has requested a special use permit to conduct maintenance on their existing natural gas pipeline west of Highway 53 within an existing right-of-way authorized by BLM Right-of-Way Grant, Serial # ILES-058112.
Project Summary
Location Summary:
Within the Midewin National Tallgrass Prairie on the west side of State Road 53 and railroad tracks, and east of Henslow Trail in T33N R09E Section 13.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 09/19/2024 |
| Decision | 10/2024 (Estimated) |
| Implementation | 10/2024 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Midewin National Tallgrass Prairie All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations; Natural Gas
Current Status:
Completed
Project Decision Information
Nicor Gas Natural Gas Pipeline Maintenance 2024
Decision Signed Date: 10/10/2024
Forests:
Midewin National Tallgrass Prairie
Districts:
Midewin National Tallgrass Prairie All Units
States:
Illinois
Counties:
Will
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Shanna McCarty
30239 South State Route 53
Wilmington, IL 60481
815-423-2114
shanna.mccarty@usda.gov