Millstone Water District Right-of-Way Renewal Proposal
Proposal would renew a right-of-way access (special-use permit) for the continued operation and maintenance of 21.01 miles of a buried potable water transmission pipeline system across Forest land.
Project Summary
Current Status:
Completed
Location Summary:
Pope County
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 10/11/2012 |
| Comment Period | 10/11/2012 |
| Decision | 02/2013 (Estimated) |
| Implementation | 02/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (15)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Shawnee National Forest All Units
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Project Decision Information
Millstone Water District Right-of-Way Renewal
Decision Signed Date: 02/14/2013
Legal Notice Date: 02/17/2013
Forests:
Shawnee National Forest
Districts:
Shawnee National Forest All Units
States:
Illinois
Counties:
Pope
Legal Land Description:
Sections (sec) 34 & 35, Township 11 South, Range 5 East; and sec. 22, 27, 28, T12S, R6E; and sec 9, T11S, R6E; and sec 10, 13, 15, & 16, T12S, R5E: and sec 2, 3, 4, 6, 19, 29, 30, 31, & 32, T13S, R5E;
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Robert Monroe
50 Highway 145 South
Harrisburg, IL 62946
618-658-2111
robertmonroe@fs.fed.us