Equality Cave Bat Gate
We are proposing to construct a bat gate and institute a seasonal closure at Equality Cave (Cave Hill Cave). The cave would be closed to the public from October 1 through April 30 and entry from May 1 to September 30 would be by permit only.
Project Summary
Location Summary:
Cave Hill area, near Equality
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 07/06/2006 |
Decision | 02/2007 (Estimated) |
Implementation | 05/2007 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (6), 36 Cfr 220.6(E)(6)
Special Authority:
Forest Service Energy Implementation Plan
Lead Management Unit:
Hidden Springs Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Wildlife, Fish, Rare Plants
Project Activity:
Species Habitat Improvements
Current Status:
Completed
Project Decision Information
Equality Cave Bat Gate
Decision Signed Date: 02/09/2007
Forests:
Shawnee National Forest
Districts:
Hidden Springs Ranger District
States:
Illinois
Counties:
Saline
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Rod McClanahan
602 N. First Street
Vienna, IL 62995
618-658-2111
rmcclanahan@fs.fed.us
Last Updated: 4/7/2011