Natural Gas Pipeline Permit Amendment
Amend an existing permit to include a communication tower on about 0.2 of an acre within their existing permit area.
Project Summary
Location Summary:
East side of Route 3 north east of Gorham
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 07/06/2007 |
Decision | 05/2008 (Estimated) |
Implementation | 05/2008 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Mississippi Bluffs Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Natural Gas Pipeline Permit Amendment
Decision Signed Date: 05/22/2008
Forests:
Shawnee National Forest
Districts:
Mississippi Bluffs Ranger District
States:
Illinois
Counties:
Jackson
Legal Land Description:
9 ESouth 3 West section 20
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Marlene Rivero
521 N. Main St
Jonesboro, IL 62952
618-833-8576
mrivero@fs.fed.us
Last Updated: 6/27/2008