Southern Illinois Power Cooperative Right-of-Way
Proposal would renew a special-use permit authorizing the continued operation and maintenance of overhead 69 KV electric power transmission lines on Forest land.
Project Summary
Location Summary:
On Forest land located in Jackson, Johnson, Union, and Gallatin Counties, IL
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 10/11/2012 |
Comment Period | 10/11/2012 |
Decision | 02/2013 (Estimated) |
Implementation | 03/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (15)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Hidden Springs Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Southern Illinois Power Cooperative Right-of-Way
Decision Signed Date: 02/14/2013
Forests:
Shawnee National Forest
Districts:
Shawnee National Forest All Units
States:
Illinois
Counties:
Gallatin; Jackson; Johnson; Union
Legal Land Description:
sec 31, T10S, R1W, and sec 6, T10S, R2W, and sec 9, 10, 13, 16, T10S, R7E, and sec 18, 14, T10S, R8E, and sec 24, T11S, R1E, and sec 9, T12S, R3E, and sec 29, 31, T12S, R7E,
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Robert Monroe
602 N. First Street
Vienna, IL 62995
618-658-2111
robertmonroe@fs.fed.us
Last Updated: 3/28/2013