Waterfall Stewardship Pilot Project
This project proposes to improve forest health and sustainability of the oak-hickory ecosystems, improvement of wildlife habitat, and reduction/control of non-native species.
Project Summary
Location Summary:
This project area is north of Illinois Route 3, east of Illinois Route 151, south of Gum Ridge Road, and west of Buttermilk Hill Road.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 09/19/2018 |
Comment Period | 02/13/2019 |
Objection Period Start | 06/16/2019 |
Decision | 12/2019 (Estimated) |
Implementation | 01/2020 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Mississippi Bluffs Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Vegetation Management (Other Than Forest Products); Watershed Management; Forest Products; Wildlife, Fish, Rare Plants
Project Activity:
Forest Vegetation Improvements; Timber Sales (Green)
Current Status:
Completed
Project Decision Information
Waterfall Stewardship Pilot Project
Decision Signed Date: 12/10/2019
Forests:
Shawnee National Forest
Districts:
Mississippi Bluffs Ranger District
States:
Illinois
Counties:
Jackson
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Justin Dodson
521 N. Main St
Jonesboro, IL 62952
618-658-1316
jddodson@fs.fed.us
Last Updated: 2/24/2020