Oliverian Stewardship Project
Integrated stewardship project. Goals include improvement of quality of timber stands, enhancement of wildlife habitat, mitigation of effects of past logging practices within recent Twin Oaks land acquisition, provide access and day use to Owls Head.
Project Summary
Current Status:
Completed
Location Summary:
near Oliverian Pond, Town of Benton, Grafton County, NH
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 04/11/2008 |
| Comment Period | 12/03/2009 |
| Decision | 03/2010 (Estimated) |
| Implementation | 12/2010 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Stewardship Contract, Consolidated Appropriations Resolution Of 2003
Lead Management Unit:
Pemigewasset Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Recreation Management; Forest Products; Land Management Planning; Vegetation Management (Other Than Forest Products)
Project Activity:
Facility Improvements/Construction; Forest Vegetation Improvements; Species Habitat Improvements; Timber Sales (Green)
Project Decision Information
Oliverian Stewardship Project
Decision Signed Date: 03/02/2010
Legal Notice Date: 03/04/2010
Forests:
White Mountain National Forest
Districts:
Pemigewasset Ranger District
States:
New Hampshire
Counties:
Grafton
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Brett Bayer
Forest Headquarters
Campton, NH 3223
603-536-6133
bbayer@fs.fed.us
Last Updated: 3/4/2010