Pemi Northwest Project
This project proposes vegetation management and improvements to wildlife habitat, recreation and watershed resources.
Project Summary
Current Status:
Completed
Location Summary:
Towns of Benton, Easton, Woodstock and Landaff, NH
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 05/12/2011 |
| Comment Period | 10/31/2012 |
| Decision | 02/2013 (Estimated) |
| Implementation | 08/2013 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Pemigewasset Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Fuels Management; Vegetation Management (Other Than Forest Products); Watershed Management; Road Management; Forest Products; Recreation Management
Project Activity:
Road Decommissioning; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Dispersed Recreation Mgmt.; Species Habitat Improvements; Heritage Resource Management; Trail Management; Road Maintenance; Scenery Management; Timber Sales (Green); Watershed Improvements
Project Decision Information
Pemi Northwest Project
Decision Signed Date: 02/15/2013
Legal Notice Date: 02/15/2013
Forests:
White Mountain National Forest
Districts:
Pemigewasset Ranger District
States:
New Hampshire
Counties:
Grafton
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Kori Marchowsky
Forest Headquarters
Campton, NH 3223
603-536-6108
kmarchowsky@fs.fed.us
Last Updated: 2/15/2013