Forest-wide Outfitter & Guide Conversions
In accordance with changes in national policy, all Outfitter & Guide permits (currently 1 year temporary permits on the WMNF) will be issued as 10 year permits. Permitted activities will remain the same. Operating plans and proposed itineraries will still require annual Forest approval.
Project Summary
Current Status:
Completed
Location Summary:
Across the White Mountain National Forest
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 02/05/2013 |
| Comment Period | 02/14/2013 |
| Decision | 05/2013 (Estimated) |
| Implementation | 06/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (15)
Special Authority:
Not Applicable / Other
Lead Management Unit:
White Mountain National Forest All Units
Notice and Comment Regulation:
215
Project Purpose:
Recreation Management; Special Use Management
Project Activity:
Special Use Authorizations
Project Decision Information
Outfitter & Guide Ten Year Special Use Permits Decision Memo
Decision Signed Date: 05/17/2013
Forests:
White Mountain National Forest
Districts:
White Mountain National Forest All Units
States:
Maine; New Hampshire
Counties:
Oxford; Carroll; Coos; Grafton
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Marianne Leberman
71 White Mountain Drive
Campton, NH 3223
603-536-6236
mleberman@fs.fed.us
Last Updated: 5/24/2013