Godfrey Dam Solar Panel Array
Update special use permit to allow installation of a 9-panel solar array on a single pole mount that will be placed on a 6' by 6' concrete pad. Array would be placed adjacent to an existing storage shed at the Godfrey Dam site.
Project Summary
Current Status:
Completed
Location Summary:
Godfrey Dam
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 06/14/2013 |
| Comment Period | 06/14/2013 |
| Decision | 08/2013 (Estimated) |
| Implementation | 08/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Androscoggin Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Project Decision Information
Brelin Water Works Godfrey Dam Solar Panel Installation Project DM
Decision Signed Date: 08/21/2013
Forests:
White Mountain National Forest
Districts:
Androscoggin Ranger District
States:
New Hampshire
Counties:
Coos
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Thomas Moore
300 Glen Rd
Gorham, NH 03581-1399
603-466-2713 x226
tmmoore@fs.fed.us
Last Updated: 8/21/2013