Corridor 19 Bridge Replacements
The Forest proposes to replace two bridges along Corridor 19, the road is used as a snowmobile trail in the winter season.
Project Summary
Current Status:
Completed
Location Summary:
Forest Service Road Corridor 19, about two miles west from State Highway 113B in Chatham, Carroll County, New Hampshire.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 03/31/2021 |
| Decision | 06/2021 (Estimated) |
| Implementation | 07/2021 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (4), 36 Cfr 220.6(D)(4); 32.2 (22), 36 Cfr 220.6(E)(22)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Saco Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Road Management; Recreation Management
Project Activity:
Road Improvements/Construction
Project Decision Information
Corridor 19 Bridge Replacements
Decision Signed Date: 06/15/2021
Forests:
White Mountain National Forest
Districts:
Saco Ranger District
States:
New Hampshire
Counties:
Carroll
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Brian Johnston
33 Kancamagus Highway
Conway, NH 03818
603-466-2713
bmjohnston@fs.fed.us
Last Updated: 6/15/2021