Eversource O154 T-Line Rebuild
Eversource proposes to rebuild the O154 115-kV transmission line within the existing right of way. The entire O154 line consists of 137 structures, 8 of which occur on Forest Service lands in the town of Stark, NH.
Project Summary
Location Summary:
About 3 acres of National Forest System lands in the Town of Stark, New Hampshire, just south of state highway 110.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 03/31/2022 |
Decision | 10/2022 (Estimated) |
Implementation | 02/2023 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
White Mountain National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Eversource O154 T-Line Rebuild
Decision Signed Date: 10/20/2022
Forests:
White Mountain National Forest
Districts:
Androscoggin Ranger District
States:
New Hampshire
Counties:
Coos
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Marianne Leberman
71 White Mountain Drive
Campton, NH 3223
603-536-6236
marianne.leberman@usda.gov